Waukesha P48GLD biogas CHP unit with Stamford 910 kVA generator, used

Price on request
Used biogas CHP generator set with Waukesha P48GLD gas engine, Stamford HC.1624M2 910 kVA alternator and an additional dismantled generator.

Available immediately
Only 1 available
1

Waukesha P48GLD biogas CHP unit with Stamford 910 kVA generator, used

Used biogas CHP generator set with Waukesha P48GLD gas engine, Stamford HC.1624M2 910 kVA alternator and an additional dismantled generator.

Function and possible applications

The set originates from a biogas plant and couples a gas engine to an alternator. The recorded equipment includes controls, pumps and a plate heat exchanger.

Equipment and technical data from original inventory

The following specifications are reproduced from the original German inventory to preserve model numbers and technical details.

  • BHKW Blockheizkraftwerk mit 910kVA Stromerzeuger aus einer Biogasanlage mit Gas Motor Waukesha Model: P48GLD
  • 1 Generator komplett
  • 1 Generator zerlegt als Ersateilspender (oder Wiederaufbau)
  • Hersteller: Zantingh Groep Holland
  • Type: Tantec 630 HR Motor 1-2
  • Ser.Nr.: 975100
  • Bj.: 1997
  • Gesamtgewicht Motor 1: 17000 kg
  • Generator
  • Hersteller: Stamford
  • Typ: HC.1624M2
  • Nr./Bj.: C077726-02/1997
  • AVR - Mx321
  • Leistung: 910 kVA, 1500 U/min
  • 400 V; 1313,5 A; 50 Hz; IP22
  • Dieselmotor/Gasmotor
  • Hersteller: Waukesha
  • Model: P48GLD
  • Nr./Bj.: 80464-01/1997
  • Treibstoff: Nat.-GAS / Biogas
  • Leistung: 726 kW; 1500 U/min
  • weitere Komponenten
  • Steuer-/Schaltschrank von nib-elektrotechniek mit Zantingh Master-Control
  • Grundfos Pumpen
  • Plattenwärmetauscher
  • Schalldämpfer
  • Container Maße
  • Breit ca. 3,70 m
  • Hoch ca. 3,50 m
  • Container 1 Lang  8,80 m
  • Container 2 Lang 7,00 m
  • Artikelstandort: D-01587 Riesa
  • Weitere Suchbegriffe: Bio-Gas Stromaggregat, Gas Stromerzeuger gebraucht

Condition and notes

Inventory states one complete generator and another dismantled for spares. Operational status, emissions compliance and exact scope of supply require confirmation.

Used equipment; scope and condition should be checked against the photographs and during inspection.